Check for obstacles and Fresnel zone clearance |
 |
Determination of MW antenna height from ground |
 |
Verification of LOS: Our Engineers prior to MW Installation also do Line Of Sight between
these two sites and this. The following are the equipments used by our surveyors to complete the
process successfully: |
| |
 |
GPS |
 |
Binoculars |
 |
Altimeter |
 |
Compass |
 |
Digital Camera |
 |
Topographic maps |
 |
Preparation of reports: All the obstruction which are observed in the path are recorded
and applied in to the Software of PATHLOSS to get determine the height with reference
to AMSC (Average Mean Sea Level) of MW antenna and Azimuth be installed to get the
LOS cleared. |
|